The ambitious plan for the construction of the Pantheon data center Pantheon in Topusko to begin as early as 2027 is becoming increasingly difficult to achieve. The amendments to the Spatial Plan of Sisak-Moslavina County, without which the project cannot proceed towards permits, are still not completed, and the Ministry of Environmental Protection has now determined that as part of the strategic assessment, a Main Assessment of Acceptability for the ecological network must also be conducted.
The strategic study needs to be further supplemented precisely because the Topusko Campus was subsequently included in the amendments to the Spatial Plan in March, for which the Ministry has determined that the possibility of significant negative impacts on the ecological network cannot be excluded.
The process of adopting amendments to the Spatial Plan will thus be further delayed, although the fifth amendments and supplements to the Spatial Plan of Sisak-Moslavina County were initiated back in 2021. During 2022, a Strategic Study was prepared, and the proposed amendments to the Plan went through public discussion. However, the process was not completed afterward as both the Plan and the Study were further modified and refined.
New versions of the Plan and the Strategic Study were being developed during 2024 and 2025, but the amendments were still not adopted. In March 2026, their scope was again expanded, including the Topusko Campus, i.e., the interventions necessary for the planned data center and the corresponding energy infrastructure. Due to this expansion, a new preliminary assessment of acceptability for the ecological network was requested from the Ministry.
In September, the Ministry concluded that significant negative impacts on the ecological network can no longer be excluded.
We asked Domagoj Vranješ, the owner of Vita Project, a consulting company specializing in sustainable development and green transition, to estimate how long this process might take.
The Ministry has not yet received a request
– According to regulations, when an opinion is issued that significant impacts on the conservation objectives and integrity of the ecological network cannot be excluded for a strategy, plan, or program, a comprehensive strategic environmental impact assessment must be conducted, which includes a chapter on the main assessment of acceptability for the ecological network. Therefore, this is not a separate, parallel process, but a strategic assessment that encompasses that evaluation as well. In this case, this process follows the procedure for the development and adoption of the Spatial Plan of Sisak-Moslavina County – explains Vranješ.
According to him, such a process can take between six and 12 months, but even longer.
It is important to distinguish between amendments to the Spatial Plan and the assessment of the impact of the data center itself. The Spatial Plan establishes the planning assumptions for the realization of interventions at a specific location, while the impact of a specific project on the environment is assessed separately, based on its actual technical solution.
The Ministry of Environmental Protection and Green Transition confirmed to Lider that it has not yet received a request for the implementation of the procedure for the environmental impact assessment, the procedure for assessing the need for an environmental impact assessment, nor a request for an opinion on the need to conduct these procedures for data centers in Topusko and Nova Gradiška.
This means that environmental procedures for the projects themselves, according to the Ministry’s data, have not yet been formally initiated. In the case of Pantheon, this is quite understandable as the environmental procedure cannot be initiated while the intervention is not included in the spatial plan.
In the environmental impact assessment process for a specific intervention, possible direct and indirect impacts of the specific intervention on land, soil, water, air, climate, forests, population and human health, plant and animal life, biodiversity, landscape, material property, and cultural heritage are determined. If relevant for the project, its susceptibility to the risk of major accidents or disasters is also considered.
Key prerequisites
The assessment is conducted based on the Environmental Impact Study, which must also cover the use of natural resources and the impact of the intervention on water and water bodies. Cumulative impacts in relation to existing and already approved interventions are also taken into account. But what does such a procedure look like and how long can it take?
The process depends on the type, size, and characteristics of the project. For interventions subject to so-called screening, an assessment of the need for an environmental impact assessment, i.e., OPUO, is first conducted. In this process, the competent authority obtains opinions from other institutions and local government units, informs the public, and determines based on prescribed criteria whether a full environmental impact assessment is necessary for the specific intervention.
If it is determined that a full assessment is necessary, or if it is an intervention for which it is mandatory according to regulations, the investor initiates the environmental impact assessment process, i.e., PUO. The mandatory part of the request is then the Environmental Impact Study, which is prepared by an authorized person.
The Study is reviewed by a professional committee, which assesses its completeness, after which the documentation is sent for public discussion. Based on the Study, the committee’s opinions, and the results of the public discussion, the competent authority issues a decision on the acceptability of the intervention for the environment. If the project may also affect areas of the ecological network, the assessment of its acceptability for the ecological network is included in the process.