The state needs to react because 90 percent of public procurement tenders for construction works have extended construction deadlines and increased costs, it was stated on Wednesday during the 3rd annual conference of the Croatian Chamber of Economy on public procurement for construction works.
Attorney Mićo Ljubenko from the Law Office Ljubenko & partners believes that the most pressing issues currently relate to foreign bidders, followed by the problem of project extensions and unforeseen costs. He stated that there is almost no significant project without an extended deadline, which causes additional financial costs.
– If 90 percent of tenders have extended deadlines and unforeseen costs, it means that action needs to be taken in some way – said Ljubenko.
When it comes to foreign bidders outside the EU, mainly from China, Turkey, and India, he recommends checking their references, as such companies do not have publicly available data.
– This is not the EU where you can see what everyone has done with one click – emphasized Ljubenko, adding that another recommendation is for companies from third countries to enter into a strict regime of compliance with the Croatian collective agreement for construction.
The collective agreement for wages is the same for domestic and foreign workers, and it cannot happen that foreign bidders, who may be coming to Croatia for the first time, have a more favorable position regarding collective agreements, he emphasized.
He proposes an automatic control method whereby companies working in public procurement must present a union certificate every six months confirming compliance with the collective agreement.
State Secretary in the Ministry of Physical Planning, Construction, and State Property Tonči Glavinić stated that the construction sector has been continuously growing in recent years. He believes that a positive investment climate has been created in Croatia, with a large number of private investments and public investments from the budget and EU funds.