Croatian Highways (HAC) plan to utilize unused areas along the highways for the installation of solar power plants and their own electricity production, aiming to reduce electricity costs, increase energy independence, and modernize highway infrastructure. Following a public tender conducted in February, a contract was signed for the development of conceptual designs for solar power plants at four locations along the stretch from Zagreb County to eastern Croatia, covering a total area of approximately 36 hectares.
The areas in question are the rest areas Zagreb (Plitvice) and Rastovica, as well as the junctions Sredanci and Ivanja Reka. The most favorable bidder selected is the Zagreb company ETS FARAGO d.o.o., with a contract value of 11,400 euros excluding VAT. The deadline for completing the complete documentation is March 2026, after which a decision on entering the investment will follow.
Four locations, 36 hectares of panels
The Plitvice solar power plant will be built in the area of the Zagreb (Plitvice) north rest area, on a gross available area of about 2.5 hectares. Near Županja, the Rastovica solar power plant is planned on the southern side of the rest area in Vukovar-Srijem County, covering about 3.1 hectares.
The Sredanci solar power plant will encompass two cadastral parcels in the area of the Sredanci junction in Brod-Posavina County, with a total gross area of about 11 hectares. The largest is planned in the zone of the Ivanja Reka junction in Zagreb County, on three cadastral parcels with a total gross area of approximately 18 hectares. Designers must ensure maximum utilization of each location.
Three scenarios
For each location, three variants of conceptual designs must be developed. The first scenario anticipates electricity production primarily for HAC’s own needs, with excess being fed into the electricity grid. The second model is the classic ‘production for the grid’, meaning the delivery of all produced energy to the operator. The third option combines self-consumption with the accumulation of excess energy in storage systems, such as battery systems.
– The contracted conceptual designs also include an assessment of investment costs and a feasibility analysis. Based on the results of these analyses, Croatian Highways will plan further steps, including the selection of a financing model, which may include own funds, applications for EU funds, or other appropriate financing models – they say from HAC.
If the analyses confirm the justification of the investment, HAC estimates that the first solar power plants could begin construction in 2027.
How much electricity?
Regarding expected production, HAC emphasizes that they currently have preliminary estimates indicating that the annual electricity production at the four observed locations could amount to approximately 6.3 GWh/a, 3.8 GWh/a, 1.3 GWh/a, and 1 GWh/a, depending on the location.
– Since the subject contract will be concluded in March 2026, we note that the conceptual designs are still in development and the values presented are of a preliminary nature. Actual and final values will be determined upon completion of the contract, i.e., in the final versions of the conceptual designs – they note from HAC.
