The energy future of Croatia can be bright, but for now it is not. This conclusion could be drawn from the last panel at the Lider conference of the same name, where Ivo Milatić from the Ministry of Economy and Sustainable Development, Marija Šćulac Domac from the Croatian Chamber of Economy, Maja Pokrovac from the Renewable Energy Association, Željko Vrban from HERA, and Marijan Cenger from the Croatian Biogas Producers Association gathered. Such strong names in one place guaranteed a heated discussion, and indeed, there was no shortage of heated debate on that panel.
Who is to blame for the fact that Croatia already lacks sufficient energy projects? Each participant had their theory. For Milatić from the Ministry, the only culprit cannot be the Ministry of Economy and Sustainable Development, because, although they are under-resourced, other stakeholders in the system are not working with the dynamics they should. I mean HERA and HOPS, Milatić pointed out. HOPS, he says, has an absurd price, and HERA just accepts it, thus killing investor interest, believes the Ministry representative.
Lack of people
– By the end of July, we should know the connection price for individual projects, as well as clear rules. However, the problem lies with people; there is a lack of people, people are not applying for the jobs for which we announce tenders, salaries are what they are, we can no longer offer more, and some things simply stand still because of that – Milatić explained his “side”. He also spoke about how the connection price should be regulated better and smarter; projects in the south should have a higher price because there are already renewable energy projects there, while in Slavonia, for example, there are too few such projects, so the price there should also be more competitive.
– But the bigger problem is that we do not have enough network to which these projects can connect. How to finance new power line projects? That is a problem we need to address in the future and find a solution – Milatić said, adding that part of these infrastructure projects can be “paid” from network fees, and part from funds.
Vrban from HERA responded to Milatić’s accusations that determining the connection price is not as simple as it seems and that it is a responsible job that needs to “reconcile” all participants, including the state, investors, energy producers, operators, and the market.