Home / Business and Politics / The Renewable Energy Association of HGK Calls for Acceleration of Project Implementation and Establishment of a Working Group for RES

The Renewable Energy Association of HGK Calls for Acceleration of Project Implementation and Establishment of a Working Group for RES

In order to highlight the stagnation of investments in green energy production and propose concrete solutions, The Renewable Energy Association of the Croatian Chamber of Economy today presented a document Position Paper analyzing the current state and offering solutions to the biggest issues, namely administrative barriers in the renewable energy sector.

As noted in the introduction by Marija Šćulac Domac, Director of the Sector for Industry and Sustainable Development of HGK, the RES sector has been facing procedural issues and regulatory inconsistencies since 2016, as the adoption of a regulation governing the implementation of RES projects on state land has been awaited since then. The situation has further slowed down, and in some cases, come to a halt since 2021 when the Renewable Energy Act was adopted, but not all acts prescribed have been implemented, without which no RES project can be realized.

Specifically, the adoption of subordinate legislation is delayed by more than 430 days, and as highlighted at the conference, despite announcements from the State Secretary in the Ministry of Economy and Sustainable Development Ivo Milatić in January that they would be adopted in the first quarter of this year, these implementing regulations have not even been made available for public consultation.

Additionally, tenders for energy approval according to the transitional provisions of the Electricity Market Act are being issued slowly. In one year and two months, only 17.6 percent of requests have been resolved. The problematic fact is that even after obtaining energy approval, these projects cannot continue development due to the lack of subordinate acts related to connection to the electricity grid, specifically the Rules on Connection to the Grid and Connection Fees, it was stated at the conference.

– There have been good faith attempts from all sides to resolve the situation, and this is our contribution and a call to everyone to put this sector on solid ground as soon as possible and to define a healthy state framework so that citizens and the state receive what they deserve because we have the potential and resources for that. We hope that it will be a starting point for addressing a whole range of problems and that it will encourage all stakeholders to comprehensively and systematically regulate this area, said Šćulac Domac, concluding that citizens and employers do not deserve political maneuvering but concrete measures.

image

Marija Šćulac Domac

She also noted that last week they sent a letter to ministers Oleg Butković, Davor Filipović and Branko Bačić, to form a working group in the Government that would bring concrete tasks and conclusions, which is the ultimate goal of the RES Association of HGK.

The Position Paper document, summarizing five key problems that hinder new RES projects in Croatia, was presented by Aljoša Pleić, Deputy President of the RES Association of HGK. These five areas are the legislative framework, connection to the electricity grid, spatial planning, environmental and nature impact, and regulatory compliance. As the biggest problem, both Šćulac Domac and Pleić cited regulatory inconsistency.

Pleić therefore proposed that the already prescribed acts of the Renewable Energy Act be adopted as soon as possible, emphasizing that they are not poorly written. Furthermore, he suggests reducing administrative burdens, accelerating the transition with the help of digitalization, making the development plan for the electricity grid publicly available, and expediting the adoption of spatial plans.

– In economic entities and households, we see positive shifts in the construction of RES projects, but that is not enough. Therefore, it is essential to open new investments on state land. It is necessary to create an urgent working group that will gather all stakeholders and, in a short time, within the next three months, by summer, adopt key laws, concluded Pleić.

image

Aljoša Pleić

For this reason, the RES Association of HGK suggests as a systematic measure the initiation of the preparation of Lex Specialis for the preparation and implementation of RES project realization. They propose the establishment of an Interdepartmental Working Group, composed of representatives from MINGOR, MPUGiDI, HEP ODS, HOPS, HERA, HROTE, and representatives of the RES Association of HGK, which would reach conclusions and clear deadlines for regulatory alignment within 30 days.

Ivo Čović, President of the RES Association of HGK, added that the state does not intentionally obstruct RES projects, but it is a matter of disorganization and administrative burden of the system.

– A huge cost has been incurred by society for the procurement of expensive energy sources. This cost is measured in tens of billions of euros over the past year, as we have been purchasing gas at record high prices. That is precisely the problem. Citizens and entrepreneurs aim for the price of electricity to be as low as possible. The purpose of developing RES is to reduce the negative impact on nature and the environment in the long term, concluded Čović.