All activities regarding the floating LNG terminal on the island of Krk are proceeding according to the schedule, in accordance with the deadlines set by the European Union, which is participating in co-financing this project, emphasizes the director of LNG Croatia, Goran Frančić, in an interview with Hina.
Binding offers for capacity leasing are expected by the end of April, and by the end of the second quarter, the final investment decision.
“In the non-binding phase of the Open Season procedure, around twenty companies expressed interest in leasing capacity at the floating LNG terminal, and twelve submitted offers for leasing capacity totaling more than the initially offered capacity of 2.6 billion cubic meters of gas, which is currently allowed by the capacity of the transport gas network,” says Frančić.
He adds that the binding phase of the Open Season procedure is confidential in nature since confidentiality agreements have been signed.
>>>‘Interest is high’: 27 applications for LNG terminal tenders
“Therefore, I cannot disclose details about the interest. In addition to the companies that have already expressed their interest in the non-binding phase of the Open Season, binding offers can also be submitted by companies that have not yet expressed interest, but after a prior registration procedure. The planned deadline for submitting binding offers is the end of April 2018,” says Frančić.
Activities in accordance with the schedule
By the end of the first quarter of this year, it was planned to conduct binding leasing of terminal capacity, have a contract with partners for the construction of the pier and pipeline, as well as the procurement and management of the FSRU ship, and financing of the entire project.
When asked whether these deadlines will be met, Frančić responds that activities on the technical and commercial development of the project are currently being carried out in parallel with those involving the procurement of the FSRU ship and the selection of the EPC (engineering, procurement, and construction) contractor on a turnkey basis.
“All these activities are being carried out in accordance with the schedule and deadlines defined by the EU, considering that it finances 28 percent of the procurement of the FSRU ship, the construction of the pier with auxiliary facilities, and the connecting pipeline to the point of connection to the Plinacro transport system. Contracts will be signed subject to the final investment decision, which will be made during the second quarter of 2018,” states the head of LNG Croatia.
>>>PPD: Contract with Gazprom is safer than playing with LNG
Regarding the selection of the supplier for the ship – the floating terminal and the pier and other infrastructure, he says that the pre-qualification round in both tenders has been completed. Currently, negotiations are underway to define contractual conditions, which will result in the submission of final offers, and contract signing is expected in the second quarter of 2018.
As for the environmental impact assessment procedure for the floating LNG terminal, Frančić reminds that the public discussion on the floating LNG terminal ended on November 28 of last year. He expects that by the end of March they could receive a decision on the environmental acceptability of the floating LNG terminal with the application of prescribed environmental protection measures, monitoring of the environmental state, and reporting.
When asked when the issuance of the location permit is expected, which was previously anticipated at the end of February, he explained that it is an amendment to the already issued location permit for the land LNG terminal, which became final in September 2015, and that the expected deadline for issuing the amendment to the location permit is mid-April 2018. Frančić expects the construction permit by the end of May this year.
Project financing
When asked about the phase of work related to the financial structure and whether there are interested parties for the recapitalization of LNG Croatia and entry into a strategic partnership in the realization of the project, he notes that the financing will be project-based – 28 percent is secured through funds approved by the European Connecting Facility (CEF) for works and procurement of the FSRU ship, while the remaining part will be secured through project financing, which is a common way of financing such projects.
A part amounting to 30 percent will be secured by the owner, and the remaining part of the funds is intended to be secured by a loan.
Defining the ownership structure is underway, says Frančić, reminding that a public call for investment in the company LNG Croatia was conducted in 2015 and that three preferred partners were selected, which were confirmed by the Government in July last year.
“We are now in the negotiation phase with the current owners, HEP and Plinacro, and the preferred partners regarding their entry into the ownership structure of LNG Croatia,” states Frančić.
The government made a conclusion regarding the LNG terminal project in July last year, and the media subsequently mentioned three potential investors in LNG Croatia: the Spanish Enagas, Klaipedos Nafta from Lithuania, and the Marguerite investment fund.
Regarding reports that a proposal from the Lithuanian company Klaipedos Nafta has arrived at LNG Croatia for its services related to accelerating the construction of the LNG terminal on Krk, he says he can only confirm that a Technical Cooperation Agreement was signed in April 2017 between LNG Croatia and the companies Klaipedos Nafta and Enagas as service providers.