At a meeting held yesterday at the Ministry of Transport, French consultants presented the scoring results for each of the possible eight solutions for connecting the southernmost part of Croatia with other parts of the country. The Pelješac Bridge received the highest score, while the corridor through Neum came in second.
Although the corridor would be a cheaper solution, the bridge turned out to be more competitive according to that calculation. Moreover, the bridge would be built in four years, while the corridor would take 20 years, reports Večernji list.
The Croatian side did not agree with the consultants on the price of the corridor during the meeting. The consultants claim that its construction would cost 50 million euros, while the Croats assert that the price of that solution is 130 million euros, as the consultants did not include the Schengen system in their price. Other criteria used to evaluate all possible solutions include regional, ecological, technological, geopolitical, and legal aspects. When all these criteria are summed up, the bridge emerges as the best solution.
The corridor, which is twice as cheap as the bridge according to the financial criterion (whose construction is estimated at 250 to 280 million euros), faces the most problems with legal criteria, as it would be built in another country. Representatives from Bosnia and Herzegovina requested a postponement of the conclusion because they complained, according to sources, that they received the documentation too late, and they also seek to have the financial criterion carry more weight in the scoring.