Home / Business Scene / Končar reconstructs HT’s data center worth 60 million kuna

Končar reconstructs HT’s data center worth 60 million kuna

Končar and Hrvatski Telekom have signed a contract worth 60 million kuna for the reconstruction of the data center in Zagreb.

This will also be the third data center that Hrvatski Telekom will have, but the first that will fully meet the Tier 3 standard. The goal is to expand the infrastructure so that end users can have new services with a special emphasis on the ICT sector. The complete energy infrastructure will be handled by Končar, which will supply new electrical and mechanical equipment, and a total of six members of the Končar company are participating in the project. 

– Our goal is to offer our users the highest quality and best services. This is one of the steps we are taking in that direction. Our technology does not lag behind global standards in any way, and we are especially pleased that this job will be done by a Croatian company that won the contract because it is among the best in the world and not just because it is ours – emphasized the CEO of Hrvatski Telekom, Ivica Mudrinić.
The entire project on Selska Street in Zagreb will last about 16 months, and the work is being carried out on 1,000 square meters. 

– Although Končar is recognized as a manufacturer of generators and transformer stations, one of our strengths is also the ICT sector. We established a dispatch center in Croatia 27 years ago, and two years ago we were tasked with renewing it, which is rare in the world. I thank HT for their trust and for recognizing our quality, and I am confident that the project will be realized with high quality – concluded Darino Bago, CEO of Končar.