Despite frequent complaints and sharp accusations from numerous environmental organizations and many politicians regarding the negative impact of the incinerator on the environment, the head of the Economy Department of the City of Zagreb, Ladislav Prežigalo, is increasingly active and working more urgently on the completion of the technical documentation for the incinerator, valued at around 150 million euros, which is to be built in Žitnjak.
The increasing number of accusations is also evident from yesterday’s expert presentation titled “Technological Aspects of Waste Management” held by the Zagreb County. At the presentation, environmentally oriented organizations, such as Eko 2000, once again launched a series of accusations regarding the harmfulness of the incinerator, especially concerning the financial resources needed for construction. The organizations claim that the cost of recycling is up to three times lower than the costs required for building the incinerator. Prežigalo commented that a positive opinion from the Ministry of Environmental Protection, Spatial Planning, and Construction regarding the study for the construction of the incinerator is more than sufficient for him and that he will not abandon the project despite the opposition from individuals.
Prežigalo is currently most focused on the preparation of the technical documentation, which is underway. The documentation precisely determines the capacity, electricity consumption, as well as other parameters, such as filtration and the possibility of utilizing thermal energy, and the entire documentation should be completed by the end of March. After that, Prežigalo says, a location permit still needs to be obtained, which would fulfill all conditions for announcing the tender.
– We plan that the incinerator will burn about 300,000 tons of municipal waste per year and 80,000 tons of sludge. However, an incinerator is always built with a larger capacity than planned because the amount of waste is increasing – said Prežigalo. There have been numerous debates regarding the selection of the location. We have considered and examined two locations for the construction of the incinerator. One is in the area of Toplane, and the other is this one, in Žitnjaku. We must keep in mind that after we build the incinerator, we will be transporting 500 trucks of waste and sludge with a very unpleasant odor to it every day. We cannot transport that waste via routes that would further burden Zagreb’s traffic.
With the construction of the Homeland Bridge, we will transport waste along that route, so Žitnjak is the most favorable location for building the incinerator – says Ladislav Prežigalo. He emphasizes that despite numerous accusations from various green organizations, the problem of waste disposal in Zagreb must be resolved. The key reason for this is that waste can be disposed of at the Jakuševac landfill until 2012. The problem of waste disposal must be resolved by then. – There are already 13 million cubic meters of disposed waste at Jakuševac, and between 1.5 and 2 million tons can still be disposed of – says Prežigalo.